9/15/2026 Water Line Repairs
There is 106 gallons per minute going thru flow station 3, which is off of Mountainaire. The crews will start here today. This means those area getting their water thru Flow Station 3 will be without water, Once this repair is done thee crew will move to Shallow Creek.
Once Shallow creek repairs are done the crew will move to Ranger and Quirt,
Finally the crew will try to get to Trout, This is the plan for today, its a lot so it probably wont get finished today.
The guys will get it done asap.